Transparency and Transmission: Option E Costs More

The City Council did not have an alternate plan in place to ensure electric service reliability when in January 2016 it “paused” construction of the Mill Creek substation and related transmission lines. That project, which was intended to address load growth in the South and Southwest, was known as “Option A”.  Starting in mid 2016, the Council decided to study the possibility of instead building a transmission line in north Columbia. This proposal was dubbed “Option E”. Suggestions were made that Option E was likely to be less costly than Option A.  “Option E” did not, however, address the Mill Creek substation or the substation overloading that the new substation was intended to address.

In the fall of 2017, almost a year and a half after the “pause”, the Council approved, at a combined cost of almost $200,000, two consulting contracts related to electric service. The first, a contract to look at the engineering and estimated cost of “Option E” was awarded to Burns & McDonnell.  The second, a contract to review electric service loads and electric distribution needs, was awarded to Quanta Technology. Both consultants sent their final reports to the City in July, 2018. We recently received these reports  through an open records request.

The cost estimates provided by Burns & McDonnell show Option E to be over $10,000,000 more expensive than the “paused” line, known as Option A.

The report also calls into question other arguments made by Council members who voted to pause Option A. For example, the Burns & McDonnell report confirms that the staff’s choice of metal poles for a 164 kV line was sound. (As the report states on “wood vertical monopole construction is impractical, as structure loading would exceed the capacity of an H6 wood pole” (p. 4-5); and also observes on p. 4-6: “[s]teel generally has a longer service life than wood and is not subject to rot, woodpecker damage, or other premature structure deterioration”). The report also documents the fact that Option E, like Option A, would impact residential neighborhoods (p. 7-2).  Although the report concludes that the “proposed route is feasible,” it qualified that conclusion, stating “there are a number of route obstructions which will need to be addressed and will ultimately have additional costs that would not be recognized from an unobstructed route” (p. 9-1).

Even though the Quanta report focused on overall system loads and did not look at substation level forecasts, it identifies the Perche Creek substation as needing careful monitoring during July as well as the creation of “an offloading schedule that should be triggered in case category P1 operation conditions occur (e.g. transformer failure)”. Transformers are generally manufactured for a 20 to 30 year life.  The oldest transformer at Perche Creek was manufactured in 1968, and the most recent in 1997.  The other two were manufactured in 1983 and 1986.

Another concern raised by the Quanta report is its suggestion that the City might look at changing the methodology traditionally used to ensure reliability when calculating the load serving capacity of its substations.  The purpose of  substituting a new methodology would be to “provide the opportunity to defer substation investment” (p. 29). Quanta goes on to note that selection of an alternate methodology would be dependent on “the level of risk tolerance which they [Water & Light] have regarding substation operation.”

What is our risk tolerance when it comes to electric service outages? Our homes, our businesses, and our medical facilities are entirely dependent on reliable on electricity.  The costs of an extended outage would be significant.  How close do we want to come?  The question should not be how to defer needed investments for as long as possible, but to ensure reliable service, both currently and for the long term.  As we have stated before, we need a decision-making approach that that is more proactive, transparent, and focused on ensuring our infrastructure needs are timely met in a cost-effective way.  Suggestions for how we might improve on the current process are welcome.

Keeping An Eye On Our Electric Service

We have previously discussed the Council’s ongoing failure to address the overloading of the substations that serve the South and Southwest and also affect power downtown. The overloading has only gotten worse. In 2015 the Perche Creek substation exceeded its loading goal by 22%. In 2017, that number was 29%. In July of 2018, it was 48%. Perche Creek was not the only substation to exceed its loading goals in July. Blue Ridge, Rebel Hill, and the Power Plant all exceeded 100% of their loading goals. Hinkson Creek was at 99%.

Electric systems must have reserve capacity for times of high loads and/or problems with the system such as those caused by storms, to avoid outages. This overloading is a current issue, not one for future planning. We were lucky this year. What might have happened had we had longer stretches of extreme heat as we did in 2011?

Until put on hold by the City Council, installation of the Mill Creek substation was part of Water & Light’s contingency plan to keep the system up and running under adverse conditions. (Compare these 2016 maps which show the system without Mill Creek, and with its addition.)  Load shedding” is a focus of the current plan. This was explained to the City Council in January 2018, although it did not draw much discussion. Where would outages occur? Depending on where the load needed to be dropped, outages would start with the circuits tied to that particular substation and after that, would occur on circuits identified “from a priority or community impact relationship.” (Minutes, January 2, 2018, pp. 13 and 14.)

How would your business, residence, or our community be affected by an extended outage? Is this a risk we are willing to simply live with? If not, speak up! Electric infrastructure takes time to plan and install. We have 11 months before next summer. This is an urgent issue that needs ongoing attention.  Can we develop an action plan for Vision: Lights On!?