Vision Lights On! New Report Confirms Perche Creek Risk

Again we have been lucky to have a cool Spring. As hot weather arrives, though, it’s time for another reminder that our Council unnecessarily placed our electric service at risk when it voted to “pause” the transmission line planned for the Southwest, with no alternate plan in place.

Now yet another consultant has confirmed that yes, the Perche Creek substation is overloaded. In a presentation sent to the Integrated Electric Resource and Management Plan Task Force, the engineering firm assisting the task force (Siemens) confirms that the substation has exceeded its firm capacity (in fact is currently operating at 150% of firm capacity at peak temperatures) and that its associated feeders are overextended.

As we have pointed out before, this puts us at risk for serious outages. A failure at Perche Creek would affect everyone in Columbia. Note that both the McBaine Water Treatment Plant and the Gillespie Bridge Sewer Treatment Plant are served by the Perche Creek substation. Due to the failure to build the transmission line, these facilities are not backed up the way Water & Light had planned or would like to them to be.

The pandemic has given us ample illustration of the fact that when those in leadership positions ignore or deny latent but serious risks, the potential harm to citizens increases. When the line was paused it was on-time, on-budget, and fully funded. During the last five years, we have paid millions in increased rates (which were approved but not “paused” by the Council) without getting the promised return.

It is unlikely that at this point we will be able to fix our electric infrastructure without paying out millions more. We should, however, be able to get a full accounting of what the Council’s “pause” has cost us, put in the infrastructure needed to ensure the reliability of key services, and adopt procedures to ensure that the Council cannot in the future so easily and heedlessly derail key projects that the public has already approved and paid for.

Will You Be Able To Keep Your Electric Service?

Tad Johnsen, our Water and Light Director, is retiring after many years of working to ensure the reliability of our electric system.  His final report  to the Water and Light Advisory Board contained some concerning statements.

Referencing the Council’s recent focus on renewable energy, he stated:

In the future, electric utilities will need to make the transition from the provider of electric service to providing the different electric services consumers want.

This raises several questions, including the following: Who will bear the cost of these different “options”? How will this affect our service reliability? Who makes a decision to move from a full service menu that provides broad benefits throughout the community to an a la carte set of options desired by some but may be costly to all?  Who is deciding what “consumers” want? Will the community be allowed to vote before there is a change?

Unfortunately, we can’t count on the Council to decide what will best ensure safe and reliable electric service at reasonable rates.  Ever since the Council “paused” a proposed transmission line with no alternative plan in place,  it has avoided talking about that issue.  Over 60% of voters approved the proposed transmission line.  That line, had it been built, would have helped assure basic reliable electric service at a reasonable cost for many years to come. Instead, we have paid millions,  associated with the Council’s delay.  The Council does like to talk about “renewable energy”. However, as we have previously explained, “renewable energy” is not a substitute for adequate transmission despite the efforts of various Council members to suggest that it is, and it is not always cost effective. 

Mr. Johnsen also cautioned:

As we push towards increased levels of renewable energy in our resource mix, we need to understand the impacts to market risk and potential impacts to electric rates these changes may have.

We do need to understand these risks,  Unfortunately, the Council has been less than transparent about the ongoing costs of its actions.

Mr. Johnsen further stated that the current Integrated Electric Resources and Master Planning process will likely affect the structure of electric service rates.  He also pointed out that the planning for implementation of the Council’s recently adopted Climate Action and Adaptation Plan “could have an impact on how all of Columbia’s Utilities provide services in the future.”

He expressed the hope that

the impact of these changes will be evaluated from different perspectives, including short term and long term financial costs, environmental impacts, and quality of life effects.

We hope so too. Although given the Council’s past lack of transparency on this issue we can’t assume that will happen.  So if you care about safe and reliable electric service, the time to get involved is now.  One way to prepare is to take one of the classes that Osher is offering on understanding your electric service.  Taking this class can help you better understand, monitor, and weigh in on emerging issues.  You can register for one of two sections, one on Monday afternoons (March 9-April 6) and one on Tuesday evenings (April 14-May 5).

Requesting Transparency for Transmission

Below is the text of a statement provided by Jim Windsor (retired Assistant Director of Utilities) at the City Council meeting on January 6, 2020.  If we want a more open and honest discussion of our electric service issues, we will have to continue to ask for it.

“Recently, five members of the Columbia City Council signed a letter that stated in part “we expect open, honest and transparent government.” As a citizen, I commend the concept; however, as a ratepayer of the electric utility, I question its validity.

Over 10 years ago, the first interested parties meeting regarding a new substation and the first Council work session on a proposed transmission line were held. That was followed by multiple interested parties meetings; council work sessions; reviews of multiple Option A routes; the development of Option B routes; more input from
residents; more council work sessions and discussions; a community review and
selection process; and, of course money being paid to consultants.

This lengthy process resulted in the purchase of property for the substation and the
selection of a route, called Option A, to connect the new substation with the Perche
Creek substation.

It also resulted in a bond proposal that was presented to voters in April of 2015.
Approximately half of the total bond proposal, as outlined in the information presented to voters, was related to the transmission and substation projects.The April 2015 bond proposal was approved by 68% of voters, bonds were initially sold
worth about half of the total bond authority and rate payers received a 3% rate increase to pay for the principal and interest on the bonds.

City staff moved forward with purchase of the required substation transformers and
other equipment needed to build the new substation and connect to the Grindstone and Perche Creek substations. City staff also brought forward an authorization to proceed with the transmission line.

It was at that point that a group, unhappy with the results of the lengthy public process, came to the Council in opposition to the transmission project. In January of 2016, four years ago, the Council placed the transmission line on hold. What has happened in those four years?

The mayor suggested a different route called Option E.

Burns & McDonnell was paid $100,000 for an in-depth study of Option E and that study was completed in July 2018. Public presentation to Council was part of the contract scope-of-work but never occurred. The study shows Option E would cost a minimum of $10 million more than Option A and included a list of multiple issues that could drive the cost much higher.

Quanta was hired for an electric distribution study and was also paid $100,000. That
study was completed in July 2018 and included a public presentation as part of the
contract. That presentation never occurred. The study shows that five substations
exceeded 100% of their capacity should they lose one of their transformers. Perche
Creek substation is the most in danger at 160% and that occurs at 97 degrees.

Staff sent Council a synopsis of the Quanta report after I raised the issue earlier this year. When a member of Council asked when the last time a substation transformer had failed, staff indicated it doesn’t happen often and it had been several years. That’s true, the last time it occurred was in 2012, when the summer temperature was over 100 degrees. Summers have only reached 97 since then.

The fact that the two reports were not publicly discussed can be blamed on the previous city manager. In the spirit of open, honest and transparent government, I ask the City Council and new city manager to require those consultants to complete their contracts and publicly explain their studies.

In early 2019, the Council approved the Westbury Village development which could add over 2 megawatts of load to the already overloaded Perche Creek substation. In June 2019, the Council accepted the Climate Action Plan. That plan predicts higher summer temperatures, while also encouraging switching motor vehicle fuels and natural gas equipment to electricity. It also states that more frequent extreme weather
events increase the risk of longer, sustained power outages for the City’s electric
customers.

So, after four years, where are we –

  • we have yet another citizens committee and yet another consultant with a report due in September 2020. Let’s hope this summer doesn’t exceed 97 degrees.

Reports based summer temperatures at 97 degrees, really don’t address the issue. The
real issue is “what will happen to the electric distribution system when the summer
temperature reaches 105 degrees?” That was the temperature in 2011 when the last
system peak occurred.

Since policy will be developed that is based on the climate report then perhaps the
question should be “what will happen to the electric distribution system when the
summer temperature exceeds the previous Columbia record temperature of 113
degrees?”

I look forward to open, honest, and transparent government addressing these questions.”

Vision Lights On! More on Transparency and Transmission

Following various public comment and expressions of concern, Council requested a “report on the electric capacity and load serving reliability of the Perche Creek substation” which it received at its meeting on October 7, 2019. The report does not focus on the specific loads in the area, although it notes those are being studied.  The report does note that

“There is some concern that recent load patterns may not be representative of a ‘worst-case’ for the City.  The City has not experienced extended temperatures of 105 degrees or greater since it set its all-time peak in the summer of 2011.”

Even though the report focuses on potential loss of only one transformer and does not address a complete outage at the substation, it does reference its “Load Shed Plan” for certain contingencies.  Under that plan “[r]esidential customers are targeted to be shed first while critical services such as hospitals, fire stations and the water and wastewater treatment plants are shed last.”

At least two citizens with extensive experience in the field have submitted responses to the Council pointing out issues ignored in the report. You can review those responses here (first response) and here (second response).

In other developments worth noting, the Integrated Electric Resource and Master Plan Task Force, which was appointed by the Council, issued an RFP requesting, as part of the scope of work, a review of the existing standards of reliability. This tracks the concern we noted in an earlier post that the City might look to justify the deferral of needed investment in its transmission infrastructure by simply changing the methodology traditionally used to ensure reliability.  In July of this year the Council also approved a Climate Action and Adaptation Plan (CAAP) which includes the following recommendations: (i) “moving towards 100% renewable electricity generation”, (ii) elimination of the current limits on rate increases caused by the purchase of more expensive renewable sources, and (iii) using storage batteries and community microgrids to support grid resilience and promote reliability (see pp. 48-49). The plan did not include any analysis of the costs or effects of these recommendations. The first two of these recommendations were among the CAAP priorities that were also reviewed by the Council on October 7, 2019.

So where are we going with our electric service?  Will we have an true open discussion of the trade-offs between cost, reliability, and available options or will some options like the transmission line simply remain off the table?  What is our risk tolerance?  And will we have a full accounting of the costs associated with the Council’s hasty decision to “pause” the transmission line in 2016, including an accounting of costs associated with opportunities lost when a project that was approved by the voters, on-time, and on-budget, was simply set aside.

 

Vision Lights On! Transparency, Transmission, and Summer Heat

Although the words “transparency” and “infrastructure” were used a lot in the recent mayoral election, there was little discussion of the inadequate electric infrastructure on the southwest side of Columbia. June was thankfully cool.  But as the summer heats up, the risk of outages returns.  As we have noted before, we have an aging substation serving much of the southwest side and more than one transmission line at risk (lacking needed redundancy) in the summer heat.

Most of us are used to purchasing insurance or taking proactive, protective steps when faced with a significant risk of loss.  That is essentially what voters approved in 2015 when voting for bond funds that were to be used to fix our inadequate electric infrastructure in south Columbia.  That is what the City Council was doing when it first approved the construction of a new, strategically located, substation and transmission line, and then issued bonds, and approved a related increase in rates. The new substation and connected lines were to have been finished by now.

Unfortunately, in January 2016 the Council chose to “pause” construction with no alternative plan in place.  In effect, the City Council canceled our insurance even though we have continued to pay the bills through the increased rates.  We also paid approximately $200,000 for studies which confirmed both the substation overloading and the fact that delays are costing us significantly.  Yet these studies and their implications were never publicly addressed.

Instead, the Council has added additional load by approving construction of the Westbury subdivision, sidelined our experienced staff on planning issues by referring these to a citizen commission whose members are appointed by the Council, and allowed an exodus of experienced line workers (who work to restore service when outages occur) by not paying competitive salaries. These actions only increase the risk and the need to find solutions.

What the Council does like to talk about is renewable energy.  Although renewable energy resources serve an important role in our electric system, they do not eliminate the need for investment in our transmission facilities. Ensuring adequate and reliable electric service presents many complex issues and easy answers are usually wrong. Accurate information and attention to engineering realities are needed if we are to find a way forward.

As we meet the candidates for City Manager, consider the following:  Is there a candidate who is willing to challenge the Council when it fails to consider issues that affect our health and welfare?  Or when it oversteps the bounds of our Council – Manager form of government? Or when it works to undermine our professional staff? Who is willing to talk openly and honestly to the public about both costs and risks associated with infrastructure needs and failures?  Who might move us forward?

 

Vision Lights On! Ignoring Reality

On February 4, 2019, the City Council voted for yet another development on the Southwest side. That development would place additional stress on already overloaded electric infrastructure in this part of town. Before voting, they received the warning copied below from a retired Water & Light executive.  Of course it was ignored.

Why should we be concerned about our electric infrastructure?  Keep reading! And join in Vision Lights On!

Good Morning,
Because the City Council has failed to address the electric load issue in the south part of Columbia, further development puts all southern Columbia residents at risk of outages, particularly during the summer peak season.  All development should be stopped until that issue is addressed.
I do not live in the area impacted by this overloading (or development) and I can not attend the Council meeting tomorrow night but I wanted to make you aware of this issue since it is not being addressed.
The proposed development would receive power from the Perche Substation.  That substation is loaded over 150% of design capacity.  The electric system requires redundancy.  Substations should never be loaded to the point that if one transformer fails, the load can’t be switched to another transformer.  At the Perche Substation, that point was reached several years ago and if something happens now a prolonged outage would occur.
The bond issue, that citizens passed by a large majority in 2015, would have addressed the issue by building a new substation in south Columbia; off-loading the current overloading; and, built a second transmission line to the Perche Substation (currently there is only one transmission line to Perche).  The original plan would have had the work completed by late spring 2017.
Currently there is no decision on what is to be done to address the overloading across south Columbia, yet development continues without addressing the consequences.   A study was completed several months ago that showed that the “Option E”, proposed by the mayor, would have cost nearly double the original Option A; however, that report has not been publicly discussed and nothing is being done to address the issue.
The only way this development could be serviced without attaching to the Perche Substation would be to build an “express” feeder from the Harmony Substation.  That would cost hundreds of thousands of dollars (maybe over a million) more than connecting to Perche.
I am retired now, but was responsible for forecasting electric system load.  Some Council members insist that the load hasn’t grown and therefore there isn’t an issue in southern Columbia.  There are two major flaws in that argument:
1. The historic system load occurred when the actual temperature reached 105 and the nighttime temperature never got below 80.  The recent highest summer temperatures have not exceeded 100.  Until similar high temperatures occur the actual system load can only be projected.
2. The forecast is for the “system” not for individual substations.  To be connected to the larger national grid, electric utilities have to forecast how much energy will flow into their system (transmission system) during peak conditions (subject to fines for failure).  Forecasting loads on individual substations (the distribution system) is not regulated and was not done.  As I stated previously Perche is well beyond design criteria that allows redundancy in the system.
This development should not even be discussed until the City Council addresses the electric system overloading in south Columbia.
A local attorney, with electric utility experience, has been attempting to educate the public on this issue.  For more information go to the following link
Jim Windsor
Assistant Director of Utilities – Retired

Vision Lights On! Paying Our Line Workers

Over the next few weeks as part of our Vision Lights On! effort we will be interviewing community members knowledgeable about the technical side of getting electricity to your house. Today’s guest is Jim Windsor.

1C1C: Jim, tell us a little about your background:

Jim: I retired about a year ago as assistant director of utilities for Columbia.  I started my almost 36 year career educating people on energy efficiency.  Most of my career was in the rate design, forecasting and financial management side of the utility.

1C1C: You have raised questions at the City Council about how we are paying our line workers. First tell me what does a line worker do?

Jim:  Line workers are responsible for the construction and maintenance of the electric system.  Their job is a physically demanding and extremely dangerous job, where mistakes can result in serious injury or death. Their job requires skill and training.  Line workers have to complete a four year apprenticeship before becoming a line worker.  It takes several more years of experience for the line worker to fully understand the job.  That job can be anything from fixing a street light; finding and fixing a fault in an underground feeder; building a new feeder to serve additional customers; or, going out in a storm to address an outage caused by the severe conditions. There is not a “normal day”, it is determined by the requirements of the day.

In addition to the line workers, there are also line foreman and apprentices that make up a crew.  No other City employees work on the hundreds of miles of electric system for the over 50,000 electric customers served by Water & Light.

1C1C: What is the issue with pay? Why should we care about paying market rates?

Jim:  Very simply, we are losing trained personnel to other utilities. As assistant director, I signed off on employee resignations by the director was out of town.  That was where I saw the significant problem of non-competitive pay when I signed off on the resignation of three line workers in one day.  The people that left were happy working for Columbia, but when other utilities offer them $10,000 or $20,000 more per year, they must think about what is best for their families.

Many people remember the wind event that occurred in July 2014.  At that time, there were 12 line foreman, 18 line workers and 11 apprentices.  During the recent snow event, there were only 11 line foreman, 10 line workers and 8 apprentices.  You should also know that five of the line foreman can retire any time they choose.

That is a significant loss of people. And in addition to people, Columbia lost years of experience that can’t be replaced.  The knowledge and experience of line workers that would move into line foreman positions have been lost because some of the best and most experienced line workers have gone to other utilities.

1C1C: How does this affect us as utility customers?

Jim: One effect should be apparent from the difference in available people:  Longer outages when major storms occur because the people aren’t there to respond.

What isn’t as obvious:  Maintenance doesn’t get done as quickly because there aren’t enough people.  “Contract crews” are being paid over twice as much to do work that fully staffed in-house crews could do.  The knowledge and experience of line workers that would move into line foreman positions have been lost because some of the best and most experience line workers have gone to other utilities.

1C1C: Can you think of analogy for this situation to help the reader better understand why it’s important for Council to address this pay issue.

Jim: Council “waiting on a study” or “waiting for the next budget year” is like you going out one morning and discovering a large gash in the side of one front tire.  Instead of immediately fixing it, you think “I have to get my car inspected in 9 months, I’ll wait until then”; or, “I was planning on replacing all four tires next year, it will be fine until then.” You are putting yourself at an unnecessary risk. And you are inviting unnecessary and expensive costs if the risk materializes.

1C1C: What are your recommendations for proceeding?

Jim: Columbia for some reason adopted the policy  of only paying the median of the competitive market in salary.  That policy tells everyone that half of the market is willing to pay more that the City of Columbia.  I recommend getting rid of the policy of paying the median of the competitive market.  The previous personnel study showed what the competitive salary should be and that was used as the top of the line worker salary range.  The City should be paying enough to keep existing line workers; attract qualified line workers from other utilities; and bring back some of the ones that have recently left.

1C1C: Are there other things about our electric service that concern you?

Jim:  Certainly.  The pay issue is a concern for many other important positions and must be addressed throughout the utility.  As an example, an additional electric engineer was approved for the 2018 budget year, but the utility has never been able to hire someone because it won’t offer a competitive salary.

The failure of the Council to address the system overloading in south Columbia is also a huge issue. Council stopped the substation and transmission project passed by voters in 2015 but continues to approve more and more development in south Columbia.  Some members of the Council insist that that project isn’t necessary because load hasn’t grown as once projected.  That is simply not true. The forecast they reference was for the total system, not for the distribution system off each substation.  I note that, the last system peak occurred when the actual temperature reached 105 degrees and the nighttime temperature never got below 80.  Although those conditions haven’t occurred since, the potential load has increased significantly.  I was responsible for load forecasting.  The substations serving south Columbia are overloaded.  Perche Creek, which serves the south west side of Columbia, is at 150% of its loading goal during the summer peak.  More development has been approved that would attach to that substation.  This issue must be addressed, or development needs to stop, or we will live with an ever increasing risk of significant outages and the costs and disruptions of those outages that occur.

1C1C: Thank you so much for your time.

 

Vision Lights On! Revisited

As a recent report from KOMU illustrates, Columbia is stuck in infrastructure limbo with respect to needed investment in its transmission lines and substations.  The report shows the council members who helped stop Option A, and who championed and then quietly abandoned Option E, deflecting questions by misquoting Water & Light and punting to a recently established committee whose chairperson stated it was not looking at transmission needs.

As has been explained in prior posts, we do need to strengthen our electric infrastructure now and also develop a clear plan for the future.  Ignoring this issue is like putting off buying auto insurance because there hasn’t been a crash “yet”.  Citizens deserve — but have not been getting — straightforward information, ongoing updates, and solutions that will keep the electrical infrastructure of Columbia up to par.

We invite those of you who are concerned and interested in finding a solution to join us in pursuing Vision: Lights On!  Follow this blog for future updates.

For those who are learning the history of this issue, here is an index of past posts on this topic.

Transparency and Transmission: Getting to Real Facts (9/27/18)

Transparency and Transmission: Option E Costs More (9/05/18)

More on Transmission (2/20/18)

Keeping An Eye On Our Electric Service (8/21/18)

Vision: Lights On! (2/26/18)

Our Infrastructure: Why So Little Energy Moving Forward? (7/11/17)

What Could Help Us Move Forward? (12/19/16)

Information, Misinformation, Statesmen And Politics (11/15/16)

Information And Misinformation – 1 (10/20/16)

Information And Misinformation – 2 (11/06/16)

Information And Misinformation – 3 (11/07/16)

You Can Make A Difference (10/15/16)

Improving Our Infrastructure – You Can Help! (9/19/16)

The Transmission Line: Many Questions (9/07/16)

Transparency and Transmission: Option E Costs More

The City Council did not have an alternate plan in place to ensure electric service reliability when in January 2016 it “paused” construction of the Mill Creek substation and related transmission lines. That project, which was intended to address load growth in the South and Southwest, was known as “Option A”.  Starting in mid 2016, the Council decided to study the possibility of instead building a transmission line in north Columbia. This proposal was dubbed “Option E”. Suggestions were made that Option E was likely to be less costly than Option A.  “Option E” did not, however, address the Mill Creek substation or the substation overloading that the new substation was intended to address.

In the fall of 2017, almost a year and a half after the “pause”, the Council approved, at a combined cost of almost $200,000, two consulting contracts related to electric service. The first, a contract to look at the engineering and estimated cost of “Option E” was awarded to Burns & McDonnell.  The second, a contract to review electric service loads and electric distribution needs, was awarded to Quanta Technology. Both consultants sent their final reports to the City in July, 2018. We recently received these reports  through an open records request.

The cost estimates provided by Burns & McDonnell show Option E to be over $10,000,000 more expensive than the “paused” line, known as Option A.

The report also calls into question other arguments made by Council members who voted to pause Option A. For example, the Burns & McDonnell report confirms that the staff’s choice of metal poles for a 164 kV line was sound. (As the report states on “wood vertical monopole construction is impractical, as structure loading would exceed the capacity of an H6 wood pole” (p. 4-5); and also observes on p. 4-6: “[s]teel generally has a longer service life than wood and is not subject to rot, woodpecker damage, or other premature structure deterioration”). The report also documents the fact that Option E, like Option A, would impact residential neighborhoods (p. 7-2).  Although the report concludes that the “proposed route is feasible,” it qualified that conclusion, stating “there are a number of route obstructions which will need to be addressed and will ultimately have additional costs that would not be recognized from an unobstructed route” (p. 9-1).

Even though the Quanta report focused on overall system loads and did not look at substation level forecasts, it identifies the Perche Creek substation as needing careful monitoring during July as well as the creation of “an offloading schedule that should be triggered in case category P1 operation conditions occur (e.g. transformer failure)”. Transformers are generally manufactured for a 20 to 30 year life.  The oldest transformer at Perche Creek was manufactured in 1968, and the most recent in 1997.  The other two were manufactured in 1983 and 1986.

Another concern raised by the Quanta report is its suggestion that the City might look at changing the methodology traditionally used to ensure reliability when calculating the load serving capacity of its substations.  The purpose of  substituting a new methodology would be to “provide the opportunity to defer substation investment” (p. 29). Quanta goes on to note that selection of an alternate methodology would be dependent on “the level of risk tolerance which they [Water & Light] have regarding substation operation.”

What is our risk tolerance when it comes to electric service outages? Our homes, our businesses, and our medical facilities are entirely dependent on reliable on electricity.  The costs of an extended outage would be significant.  How close do we want to come?  The question should not be how to defer needed investments for as long as possible, but to ensure reliable service, both currently and for the long term.  As we have stated before, we need a decision-making approach that that is more proactive, transparent, and focused on ensuring our infrastructure needs are timely met in a cost-effective way.  Suggestions for how we might improve on the current process are welcome.

Keeping An Eye On Our Electric Service

We have previously discussed the Council’s ongoing failure to address the overloading of the substations that serve the South and Southwest and also affect power downtown. The overloading has only gotten worse. In 2015 the Perche Creek substation exceeded its loading goal by 22%. In 2017, that number was 29%. In July of 2018, it was 48%. Perche Creek was not the only substation to exceed its loading goals in July. Blue Ridge, Rebel Hill, and the Power Plant all exceeded 100% of their loading goals. Hinkson Creek was at 99%.

Electric systems must have reserve capacity for times of high loads and/or problems with the system such as those caused by storms, to avoid outages. This overloading is a current issue, not one for future planning. We were lucky this year. What might have happened had we had longer stretches of extreme heat as we did in 2011?

Until put on hold by the City Council, installation of the Mill Creek substation was part of Water & Light’s contingency plan to keep the system up and running under adverse conditions. (Compare these 2016 maps which show the system without Mill Creek, and with its addition.)  Load shedding” is a focus of the current plan. This was explained to the City Council in January 2018, although it did not draw much discussion. Where would outages occur? Depending on where the load needed to be dropped, outages would start with the circuits tied to that particular substation and after that, would occur on circuits identified “from a priority or community impact relationship.” (Minutes, January 2, 2018, pp. 13 and 14.)

How would your business, residence, or our community be affected by an extended outage? Is this a risk we are willing to simply live with? If not, speak up! Electric infrastructure takes time to plan and install. We have 11 months before next summer. This is an urgent issue that needs ongoing attention.  Can we develop an action plan for Vision: Lights On!?