Keeping An Eye On Our Electric Service

We have previously discussed the Council’s ongoing failure to address the overloading of the substations that serve the South and Southwest and also affect power downtown. The overloading has only gotten worse. In 2015 the Perche Creek substation exceeded its loading goal by 22%. In 2017, that number was 29%. In July of 2018, it was 48%. Perche Creek was not the only substation to exceed its loading goals in July. Blue Ridge, Rebel Hill, and the Power Plant all exceeded 100% of their loading goals. Hinkson Creek was at 99%.

Electric systems must have reserve capacity for times of high loads and/or problems with the system such as those caused by storms, to avoid outages. This overloading is a current issue, not one for future planning. We were lucky this year. What might have happened had we had longer stretches of extreme heat as we did in 2011?

Until put on hold by the City Council, installation of the Mill Creek substation was part of Water & Light’s contingency plan to keep the system up and running under adverse conditions. (Compare these 2016 maps which show the system without Mill Creek, and with its addition.)  Load shedding” is a focus of the current plan. This was explained to the City Council in January 2018, although it did not draw much discussion. Where would outages occur? Depending on where the load needed to be dropped, outages would start with the circuits tied to that particular substation and after that, would occur on circuits identified “from a priority or community impact relationship.” (Minutes, January 2, 2018, pp. 13 and 14.)

How would your business, residence, or our community be affected by an extended outage? Is this a risk we are willing to simply live with? If not, speak up! Electric infrastructure takes time to plan and install. We have 11 months before next summer. This is an urgent issue that needs ongoing attention.  Can we develop an action plan for Vision: Lights On!?

Vision: Lights On!

In contrast to the lack of open dialogue on our electric infrastructure needs, the council has been convening public meetings around the City to talk about their new “Vision Zero” initiative to reduce traffic fatality rates. At those meetings, the City’s program manager has explained that “Vision Zero” is a data driven framework relying on the three E’s of “Engineering, Education, and Enforcement” and then noted that because this vision can “only be done with the commitment of everyone,”then “Everyone provides a fourth “E”.

If we were to adapt this “data driven” framework to “Vision Lights On!” we might be able to find a workable solution to our electric infrastructure needs: “Engineering, Education, Electrons smoothly flowing, Everyone committed to informed dialogue making this happen!

More Dialogue Tomorrow, March 21.

This month started with the coming together of the community through the True/False festival. And tomorrow we will continue to discuss thoughts on community at this month’s Community Commons. Whether you want to share the joy of celebration, the need to work together to strengthen community, or concerns re infrastructure, we invite you to join your neighbors and share what’s on your mind.

Community Commons
Tuesday, March 21, 7-9 pm
Enter the Tribune Training Room on Walnut Street, between 5th and Providence.

Sponsored by The Columbia Daily Tribune in partnership with the Kettering Foundation.

Information, Misinformation, Statesmen and Politicians

How ironic to read that the 5th Ward councilperson recently objected to pausing the design phase for a new sewer line  on the grounds that project costs would continue increasing if action were not taken soon. Ironic because the same councilperson actively supported  “pausing” construction on the new electric substation and transmission line earlier this year.  (See council minutes from January 19 ). Unlike the sewer line, whose projected costs have rapidly increased, the transmission line project was, at the time it was paused, on time and within the allocated money for the transmission and substation budget that had been presented to voters. The concern of project costs increasing was not in evidence when the council voted to pause the transmission line, and has not been much in evidence since as the project remains stalled.

Those participating in our “Community Commons” dialogue on “citizen centered planning” have been asking what citizens can do to help our leaders make better and more predictable decisions about our public infrastructure. Part of this discussion has focused on the difference between leaders who are “public servants” or “statesmen”, and those who are merely politicians. Differences identified included:

  • focusing on the common good v. catering to special interests or the loudest voices,

  • being a good steward of our public resources v. following the political winds,

  • being transparent v. “trying to control the message”, and

  • staying true to a vision and core values v. changing with the polls.

The council’s actions with regard to the transmission line have been a frequent reference point during these discussions.  The decision to pause the transmission line (which was first approved in 2013) was made as public meetings were being held on pole placement and design, in response to public opposition engendered by those meetings, and without input from the citizen led Water & Light Advisory board. Shortly thereafter, the 4th Ward council person suggested that maybe conservation could solve the the transmission issues (Note: as explained here, it won’t). In May 2016 the newly elected mayor supported the ongoing delay and suggested that a new “Option E”, might be possible based on his conversations with another electric provider.  Neither has updated the public on the feasibility of these alternatives, nor provided a timeline for their evaluation, nor provided estimates of the  costs associated with ongoing delay.  A letter sent by the Water & Light advisory board to the City Council on September 18, 2016 providing an analysis of the public concerns  and reaffirming the advisory board’s support for Option A, appears to have been largely ignored.

The recently released 2016 “Citizen Handbook” – which is offered as the City’s “performance report” to its citizens, stated (p. 8) “Wherever you live, water, sewer, electric and stormwater systems should be safe and reliable.” What are we doing to ensure that that goal is met?  Who is responsible for the costs and risks of delay when a project is “paused”?  What information should be gathered before an “alternative” is put on the table for consideration? What information should be shared with the public and when? What circumstances justify reopening decisions already made?

On p. 31, of the Citizen Handbook this report is given with respect to our electric service:

“The tricky part of getting the electricity exactly when and where it is needed is very complicated. Over the years, Columbia electric ratepayers have invested in the infrastructure to build a system that has a reliability rating of 99.9876 percent. Although the electric load growth has dropped from a 2 percent increase to a 1.25 percent growth rate, it was identified in 2007 that an additional substation and transmission lines were needed in southern Columbia. After many public meetings, gathering feedback from residents in the area and the meetings with the City Council, a route for the new transmission lines was decided at a public hearing in 2013. Voters approved the funding for the project through using bond funds in 2015. In 2016, the City Council decided to reconsider the route. At the time this article was published, a solution to electric reliability and overloading issue had not been decided by the City Council.”

How do we want our key infrastructure decisions to be made? What would best serve the common good? What can we do to ensure good stewardship of our public resources?

Join us tomorrow at the Community Commons and share your ideas.

Community Commons
Tuesday, Nov. 15, 7-9 pm
Enter the Tribune Training Room on Walnut Street, between 5th and Providence.

Sponsored by The Columbia Daily Tribune in partnership with the Kettering Foundation.

More Divides

In addition to healing divisions reflecting age, class and race,  participants in our February forum further identified a need to build bridges of communication and collaboration between City and County governments, City government and citizens, and  citizens and City staff.  The Battle students raised the question of how to strengthen connections between schools and community. Several people observed that without proactive dialogue between citizens, planners, and elected leaders, Columbia runs the risk of developing a geographic divide between North and South Columbia, like the geographic divides that exist in the St. Louis area.    Holding regular community dialogues within school buildings could begin to address some of these issues.

Other communities, including  Carbondale IL, have used sustained community dialogue to help solve difficult issues.  Columbia headed in that direction with the Imagine Columbia’s Future visioning process, although that dialogue was not sustained following that process in the ways envisioned by the public.  What could a “community commons” for dialogue look like in Columbia?  What might we accomplish by working together?