Below is the text of a statement provided by Jim Windsor (retired Assistant Director of Utilities) at the City Council meeting on January 6, 2020. If we want a more open and honest discussion of our electric service issues, we will have to continue to ask for it.
“Recently, five members of the Columbia City Council signed a letter that stated in part “we expect open, honest and transparent government.” As a citizen, I commend the concept; however, as a ratepayer of the electric utility, I question its validity.
Over 10 years ago, the first interested parties meeting regarding a new substation and the first Council work session on a proposed transmission line were held. That was followed by multiple interested parties meetings; council work sessions; reviews of multiple Option A routes; the development of Option B routes; more input from
residents; more council work sessions and discussions; a community review and
selection process; and, of course money being paid to consultants.
This lengthy process resulted in the purchase of property for the substation and the
selection of a route, called Option A, to connect the new substation with the Perche
Creek substation.
It also resulted in a bond proposal that was presented to voters in April of 2015.
Approximately half of the total bond proposal, as outlined in the information presented to voters, was related to the transmission and substation projects.The April 2015 bond proposal was approved by 68% of voters, bonds were initially sold
worth about half of the total bond authority and rate payers received a 3% rate increase to pay for the principal and interest on the bonds.
City staff moved forward with purchase of the required substation transformers and
other equipment needed to build the new substation and connect to the Grindstone and Perche Creek substations. City staff also brought forward an authorization to proceed with the transmission line.
It was at that point that a group, unhappy with the results of the lengthy public process, came to the Council in opposition to the transmission project. In January of 2016, four years ago, the Council placed the transmission line on hold. What has happened in those four years?
The mayor suggested a different route called Option E.
Burns & McDonnell was paid $100,000 for an in-depth study of Option E and that study was completed in July 2018. Public presentation to Council was part of the contract scope-of-work but never occurred. The study shows Option E would cost a minimum of $10 million more than Option A and included a list of multiple issues that could drive the cost much higher.
Quanta was hired for an electric distribution study and was also paid $100,000. That
study was completed in July 2018 and included a public presentation as part of the
contract. That presentation never occurred. The study shows that five substations
exceeded 100% of their capacity should they lose one of their transformers. Perche
Creek substation is the most in danger at 160% and that occurs at 97 degrees.
Staff sent Council a synopsis of the Quanta report after I raised the issue earlier this year. When a member of Council asked when the last time a substation transformer had failed, staff indicated it doesn’t happen often and it had been several years. That’s true, the last time it occurred was in 2012, when the summer temperature was over 100 degrees. Summers have only reached 97 since then.
The fact that the two reports were not publicly discussed can be blamed on the previous city manager. In the spirit of open, honest and transparent government, I ask the City Council and new city manager to require those consultants to complete their contracts and publicly explain their studies.
In early 2019, the Council approved the Westbury Village development which could add over 2 megawatts of load to the already overloaded Perche Creek substation. In June 2019, the Council accepted the Climate Action Plan. That plan predicts higher summer temperatures, while also encouraging switching motor vehicle fuels and natural gas equipment to electricity. It also states that more frequent extreme weather
events increase the risk of longer, sustained power outages for the City’s electric
customers.
So, after four years, where are we –
- we have yet another citizens committee and yet another consultant with a report due in September 2020. Let’s hope this summer doesn’t exceed 97 degrees.
Reports based summer temperatures at 97 degrees, really don’t address the issue. The
real issue is “what will happen to the electric distribution system when the summer
temperature reaches 105 degrees?” That was the temperature in 2011 when the last
system peak occurred.
Since policy will be developed that is based on the climate report then perhaps the
question should be “what will happen to the electric distribution system when the
summer temperature exceeds the previous Columbia record temperature of 113
degrees?”
I look forward to open, honest, and transparent government addressing these questions.”
Pingback: Will You Be Able To Keep Your Electric Service? – One Community One Columbia
Pingback: Vision Lights On! New Report Confirms Perche Creek Risk – One Community One Columbia
Pingback: Transmission 2021: Still At Risk – One Community One Columbia